Fire Codes

Question: 

We have a local builder wishing to use floor trusses with a 2-hour assembly. I have shown him the 2-hour design on pages 17-27 of the second edition of SBCA’s Metal Plate Connected Wood Truss Handbook. Is this assembly UL approved? If so, what is the design number?

Question: 

The Gypsum Association “Fire Resistance Design Manual” (GA-600-12) lists file RC2601 with two layers of 5/8 in. gypsum wallboard (GWB) on wood joists.

Question: 

Are there any published studies or guidelines on the fire rating of floor trusses built with 2x3 lumber?

Question: 

I am thinking of using wood trusses for the roofing/ceiling structural systems on some houses I shall build. I remember, though, an engineer/volunteer fireman commenting back in 1989 that the connector plates are prone to expand and pop off, early on in a fire, causing catastrophic structural failure. Was this the case, and if so, has this problem been corrected?

Question: 

How do you evaluate whether a metal plate connected truss is still usable after exposure to fire? Are there any recommended tests?

Question: 

A question has come up concerning sloped roof trusses and fire assembly ratings. Some are reluctant to rely on test results from flat (parallel chord) trusses applied to sloped roof trusses. Do you have any information regarding the suitability of the fire rated ceiling assemblies for sloped roof trusses? Does the “minimum depth” requirement of the parallel chord assembly apply to the minimum depth of a sloped roof truss (i.e., heel height?)

Question: 

I need to obtain some information on fire-retardant-treated roof trusses.

Question: 

I am trying to develop a guideline for my firefighters regarding initial fire attack in buildings with light-weight trusses. My concern is truss failure, especially when exposed to fire. Is there any information on failure time related to flame impingement? Any information about truss failure – especially in a fire condition would be helpful.

Question: 

Is it possible to construct an assembly for ceiling between first and second floors using 2x with few layers of gypsum to obtain a 3-hour fire rating?

Question: 

In a small scale multi-family residential project, I'd like to use a wood truss floor-ceiling assembly to achieve a one hour separation between units. I'd like to directly attach the drywall to the underside of the trusses & use the truss space for ducts & lighting (the floor above will be lightweight concrete on plywood sub-floor). UL assemblies do not seem to address the duct/light penetrations in such an assembly. Can I achieve a one-hour rating in such an assembly and how are penetrations addressed? Can the ducts in the truss space serve both units above and below?