Construction

Question: 

What are the requirements for installing valley sets over roof trusses? I am interested in nailing and support conditions. Some engineers ask for the bottom chord of the valley truss to be ripped to match the roof pitch of the underlying trusses. Is this necessary? How can I calculate values for uplift resistance for the building inspector?

Question: 

What are the requirements for installing “valley set” overlay roof trusses? I am interested in nailing and support conditions. Some engineers ask for the bottom chord of the valley truss to be ripped to match the roof pitch of the underlying trusses. Is this necessary?

Question: 

When you’re selling trusses through a lumberyard and the contractor calls to say that the “trusses don't fit correctly,” who has the ultimate responsibility for the trusses? I argue that the lumberyard is responsible since we have provided them with all the information on how the job was designed, even though they may or may not have passed this information on to the contractor.

Question: 

If you use hurricane clips to secure roof trusses from uplift, are you allowed to use fewer than the typical three nails in the bearing heel of the roof truss? I am concerned because we want to do the right fastening schedule, but three nails in addition to the hurricane clip splits the wood. What is the standard recommendation?

Question: 

Occasionally we deal with truss failures due to impact and or crushing forces such as trees falling onto roof structures. At what point can the truss no longer be repaired? Also, what should an adjuster look for when determining repair-ability? Or should a storm adjuster basically punt and call a consultant for every truss failure?

Question: 

We are concerned with SBCA’s BCSI-B1 Summary Sheet which under “Notes” makes a disclaimer. Our concern is if there would be an accident with our trusses and we point out that the bracing was not placed correctly according to SBCA documentation, which is sent with every job. If the accident goes to court, how will our attorney respond when the opposing attorney points out the disclaimer, which infers that the bracing we recommend must be flawed, otherwise it would not be disclaimed?

Question: 

I am looking for strongback bracing requirements for a 12 in. deep residential floor system with trusses in lengths up to 19 ft. Can the strongback bracing end at a truss without tying into an end wall? For instance, can three trusses of a type be tied together by strongbacks, then the next series of different trusses be tied together without having to be tied back to the previous type of trusses?

Question: 

Are there any published studies or guidelines on the fire rating of floor trusses built with 2x3 lumber?

Question: 

Is there a detailed table for gable studs that gives the maximum length a vertical member can be before a lateral brace is required?

Question: 

We have a customer that bought trusses in June. The trusses were shipped [ and one month later are] being set. The chords have weathered and bowed. What is the industry standard for dealing with this problem? What is our liability in this situation? We were not aware of any delays on the customer’s part and shipped as requested. Note: These trusses are 62 ft. scissor trusses.