Question: 

I am a building inspector and I have a question on information provided on truss design drawings. What does the uplift reaction number represent? Some manufacturers are very specific and state “to provide for mechanical connection of the truss to the top plate with a connector capable of withstanding a specific load.” Others simply list the uplift reaction with no further information. These are the ones that have caused a debate as to what the number actually represents.

Question: 

Can you explain drag loads and how to calculate a drag load pertaining to roof trusses?

Question: 

I am trying to develop a guideline for my firefighters regarding initial fire attack in buildings with light-weight trusses. My concern is truss failure, especially when exposed to fire. Is there any information on failure time related to flame impingement? Any information about truss failure – especially in a fire condition would be helpful.

Question: 

Does the NFPA sprinkler standard address sprinkler loading? If so, how and where do I buy it? What other information do you have on sprinkler loading? How do other truss companies price jobs for sprinkler loading the plans do not include a sprinkler layout or even say what size/type of sprinkler system will be used?

Question: 

We have a customer that bought trusses in June. The trusses were shipped [ and one month later are] being set. The chords have weathered and bowed. What is the industry standard for dealing with this problem? What is our liability in this situation? We were not aware of any delays on the customer’s part and shipped as requested. Note: These trusses are 62 ft. scissor trusses.

Question: 

I installed roof trusses in my house and dry walled the ceiling to the bottom of the trusses. Now I seem to have a problem with the change of the seasons. Where the ceiling meets the interior wall, a gap opens and closes – in winter it opens, in summer it closes. What did I do wrong, how can I correct it and how should the drywall be installed in the first place?

Question: 

It is critical that permanent top chord bracing is supplied by proper nailing of the valley truss bottom chords to the carrying truss top chords, through purlins or properly installed rated roof sheathing. If the sheathing is not carried through under the valley framing, then the permanent top chord bracing must be supplied in another manner.

Question: 

I am looking for strongback bracing requirements for a 12 in. deep residential floor system with trusses in lengths up to 19 ft. Can the strongback bracing end at a truss without tying into an end wall? For instance, can three trusses of a type be tied together by strongbacks, then the next series of different trusses be tied together without having to be tied back to the previous type of trusses?

Question: 

How do I, as a truss manufacturer, adequately advise my customer against the dangers of 60 ft. and over truss span installations?

Question: 

Is lag bolting the bottom chord of a truss to the top plate of a wall a proper fix to correct truss arching, assuming the attic is properly vented?